Track-In Sub-Material#

Overview#

This operation is used to track in a Sub-Material into a Resource, meaning that the Sub-Material begins being processed at the physical Resource. This operation can be performed from both the Material and Resource perspectives.

Setup#

No specific setup is required other than meeting the preconditions of the transaction.

Preconditions#

  • The Sub-Material is in Queued or Processed state.
  • The Sub-Material is tracked in:

    • To a direct Sub-Resource of the Resource where the Parent Material is being processed, if the Sub-Resource has Processing Type Process and System State Up.
    • To the same Resource as the Parent Material, if no direct Sub-Resource meets these conditions. Do not specify a Sub-Resource.
    • The Parent Material is in In Process state.
    • The current Step SubMaterialTrackStateDepth property is greater than or equal to the current Sub-Material depth, and the Parent Material LastProcessedResource has the IsSubMaterialTrackingEnabled property set to true.

Sequence of Steps#

Step 1: Resource State#

  1. Select the Sub-Material and select Track-In.
  2. Verify the Resource details and define the Resource State.
  3. Click Next.

Step 2: Record Loss/Bonus#

trackin_submaterial

Info

For more information, see the Sub-Material Processing tutorial.