Manage Costs#
Product.Edit
Overview#
This operation is used to define the Product costs.
Setup#
No specific setup is required other than to meet the precondition of the transaction.
Preconditions#
- The Costing module is properly licensed in the system.
- The Product exists and it is Active.
Sequence of Steps#
Step 1: Manage Costs#
If the Costing module is properly licensed in the system, the Costs tab will be enabled on the right-hand sidebar and you will be able to define the Product costing information.
- Modify the Product costs by entering:
- Initial Unit Cost - The initial cost is used to calculate the initial material cost when a material is created with this Product.
- Finished Unit Cost - The finished cost is used to forecast the cost of a Product, accounting for the incorporated materials defined in the Bill-of-Materials (BOM) with their finished unit cost.
- Select Update to complete the operation.