Complete Setup#
Resource.CompleteSetup
Overview#
This operation is used to mark the Resource as not being in setup anymore.
Setup#
No special setup is required other than to meet the preconditions of the transaction.
Preconditions#
- The Resource is of processing type Process.
- The Resource property In Setup must be
true.
Sequence of Steps#
Step 1: General Data#
- From the Material - from the Material details page, select the Complete Setup button on the top ribbon to open the wizard. Select the Resource and continue.
- If available, from the Production Order Step - from the Resource details page, go to the Schedule View, select the Production Order Step and select the Complete Setup button on the top ribbon to open the wizard.
-
From the Resource - The Resource is already selected, select the Complete Setup button on the top ribbon to open the wizard.
-
The state of the Resource is subject to being changed, by selecting a new state from the list. In case that the state transition is associated with Reasons, the user can accept the suggested Reason or select another one.
- Optionally, enter a comment.
- Select Complete to complete the operation.