Join Maintenance Activity Orders#
MaintenanceActivityOrder.Join
Overview#
This operations is used to join one or more Maintenance Activity Orders (MAOs) with a Parent MAO. When a MAO is joined with a Parent, only the Parent needs to be performed. After the Parent is completed, both the Parent and the included MAO are scheduled by the system.
Preconditions#
- All MAOs to be joined (both Parent and Child):
- Are Active and in one of these execution states: Requested, Approved or Released.
- Belong to the same Maintenance Plan Instance.
- Have the same schedule type, which must be one of the following: Usage Based, Time Based or Time And Usage Based.
- The relationship from Parent MAO and Children MAO exists in the effective Maintenance Plan.
- The Parent MAO must not be already included in another MAO.
- The user must belong to the Maintenance Plan Instance Owner Role.
Sequence of Steps#
Step 1#
- Select all the MAOs to be joined with the Parent MAO.
- Optionally, enter a Comment.
- Select Join to complete the operation.