Associate Maintenance Plan With Container#

🔒 MaintenancePlan.AssociateContainer

Overview#

The Associate Maintenance Plan with Container operation associates one or more Containers with a particular Maintenance Plan.

Setup#

No specific setup is required other than to meet the preconditions of the transaction.

Preconditions#

  • Container is Active and has no other identical Maintenance Plan currently associated with it.

  • Maintenance Plan has an Effective version.

Sequence of Steps#

The Associate Maintenance Plan with Container wizard can be called from the Maintenance Plan page within the Business Data Group.

A Container can also be associated with a Maintenance Plan directly from the Container page Maintenance View.

Step 1: Containers#

  1. Press the Associate button and from the dropdown options select Container to open the appropriate wizard.
  2. Select the Container to which the Maintenance Plan will be associated.
  3. Select the appropriate Base Date to set the date when the Maintenance Plan will start.
  4. Select the appropriate Schedule Mode (Earliest or Latest).
  5. If wished, apply the current definition to all the selected Containers by pressing the Apply Same Date To All Containers button
  6. Select Next.

mp_associate_containers_step_one

Note

For more information on Schedule Mode, see Maintenance Schedule Options.

Step 2: Activities#

  1. If wished, specify customized the Base Date and Schedule Mode for any of the Maintenance Activities that belong to the Maintenance Plan.

mp_associate_containers_step_two

Step 3: General Data#

  1. Select the owner role - the owner role represents the group of people who is able to manage the Maintenance Activity Orders under the Maintenance Plan Instance.
  2. Optionally specify a distribution list - to be used by the SendMaintenanceManagementNotificationMail rule.
  3. Press Associate to perform the operation.

Info

It is possible to define the default value for the Schedule Mode by editing the entry Context = MaintenancePlan.Associate, Element = ScheduleMode in the Generic Table GUIElementDefaultValue. The default value is Earliest.