Abort Material#
Material.Abort
Overview#
This transaction aborts a process on a Material that has been tracked in.
Note
It is only possible to abort the complete job, that is to abort the process for Top-Most Materials and not for individual Sub-Material jobs.
Setup#
No special setup is required other than to meet the preconditions of the transaction.
Preconditions#
- Material is Active.
- Material is a Top-Most Material (has no Parent Material).
- Material is not In Transit and not On Hold.
- Material is in the State In Process.
- If the Resource has the properties Enable Check-In and Require Check-In For Material Operations set to
true, and the current user Is Integration User is set tofalse, there must be an Employee associated with the user who is currently associated with the Resource. - If in the Step Enable Step Certification Requirements is set to
true, the current user Employee must have the required Certifications as defined in the StepCertificationRequirementsContext Smart Table. - Material has not been partially assembled.
-
If the Current BOM Type is Packing:
- If Material is Top-Most:
- The QuantityToPack is equal to the Material Primary and Sub-Material Quantity combined.
- The PackedQuantity is equal to the Material and Sub-Material Assembled Quantity combined.
- If Material is Sub-Material:
- The QuantityToPack is equal to the Material Primary Quantity.
- The PackedQuantity is equal to the Material Assembled Quantity.
- For the Abort to succeed, the PackedQuantity must be zero.
- If Material is Top-Most:
-
If Material Current BOM Assembly Type is Explicit Long Running, the BOM Instance referenced in the Current BOM Instance property will be terminated.
-
If the Material Current BOM Assembly Type is Weigh And Dispense (meaning that either the assembly process is not yet started or the Material is already fully assembled):
- There are no BOM Instance Item Material records associated with the Material Current BOM Instance (meaning that the assembly process has not started) or
- The BOM Instance Assembled Quantity matches the Quantity To Assemble.
-
If the Material Current BOM Assembly Type is Explicit Long Running:
- The Material Assembled Quantity must be
0. - All BOM Instance Items must have the System State set to Open and the Assembled Quantity must be
0.
- The Material Assembled Quantity must be
Preconditions for Bulk#
-
In addition to the preconditions mentioned above, all Materials must:
- Be at the same Resource and Lane.
Sequence of Steps#
Step 1#
This screen captures all the necessary information for the transaction.
- Review the Resource Details and the lane information (if configured and Is Multilane Active enabled).
- Optionally, change the State of the Resource.
- Optionally, add a comment.
- Select Abort to complete the operation.
Info
If there is an open Checklist Instance associated with the Material, it will be terminated and will no longer be associated with the Material.
Info
If a Production Order Step connected to the Resource exists and is currently In Progress, the In Progress Quantity will be set to the maximum value (chosen between the In Progress Quantity, the Material Primary Quantity, and the Material SubMaterialsPrimaryQuantity). If the In Progress Quantity is set to 0, the Production Order Step will be set as Released.