Complete Line Setup#
Resource.CompleteLineSetup
Overview#
This operation is used to Complete an ongoing setup in the Sub-Resource(s) of a Line Resource.
Setup#
No special setup is required other than to meet the preconditions of the transaction.
Preconditions#
- The main Resource is of processing type Line.
- The Sub-Resource property In Setup must be
true. - If the Sub-Resource Setup Mode is different from Not Required:
- All Documents that must have been Read and Understood were Read and Understood.
- The Resource Current Setup Checklist Instance must be Completed.
- All the Durables and Consumables must be set in the right positions and quantities.
- The Recipe, if set manually, must match with the required Setup Recipe.
- The Sub-Resource property Setup Begin and Complete Mode must be Manual Begin and Complete.
- If there are Material Line Step Resources that match the setup Material, Resource, and Step, their Setup State must be In Progress.
Sequence of Steps#
Step 1: General Data#
- Select a Resource matching the preconditions.
-
Select the Complete Line Setup button on the top ribbon to open the wizard:
-
In the Complete Line Setup (Sub-Resources) wizard select the Resource(s) you want:
-
The system will suggest a default transition, and if applicable, also a Reason, which you will be able to override.
- Optionally, enter a comment.
- Select Complete to complete the operation.
Info
You can also access the Complete Line Setup button through the Resource View.