Overview#

This operation is used to create a Sampling Plan. A template can also be created using a similar procedure and there is also the possibility of using a template to create the new object as well. This selection can be done in the main entity menu.

Setup#

No specific setup is required other than to meet the preconditions of the transaction.

Preconditions#

  • The Sampling Plan does not currently exist in the system.

Sequence of Steps#

Step 1: General Data#

  1. Provide a name for the Sampling Plan.
  2. Optionally, provide a description of the Sampling Plan.
  3. Select the Sampling Plan type (for classification purposes only). The list of possible values is taken from the SamplingPlanType Lookup Table.
  4. Specify the Default Sampling by specifying:

    • Type (CounterBased, CounterAndTimeBased, TimeBased)
    • CounterFrequency (for CounterBased, CounterAndTimeBased), a value of 10 means every tenth lot
    • TimeFrequency (for CounterAndTimeBased, TimeBased), a value, in hours

create_sampling_plan_step_one

Step 2: Context#

  1. Specify the context information for the Sampling Plan. At minimum it must have one context defined. Possible contexts are defined in the table below.
Property Description
MaterialProduct Product of the Material
MaterialProductGroup ProductGroup of the Product of the Material
MaterialProductMaturity Maturity of the Material Product
MaterialRecipe The last used Recipe of the Material
MaterialResource Resource of the Material
MaterialProcessStep Process Step of the Material (determined by the Track In of the last Step with a Processing Type of Process)
MaterialProcessResource Process Resource of the Material (determined by the Track In of the last Step with a Processing Type of Process)
MaterialStep Step of the Material
MaterialStepMaturity Maturity of the Material Step
MaterialType Type of Material
MaterialProductionOrder Production Order of the Material

Table - Possible contexts when creating a Sampling Plan