Manage Costs#
Step.Edit
Overview#
This operation is used to define the Step costs.
Setup#
No specific setup is required other than to meet the precondition of the transaction.
Preconditions#
- The Costing module is properly licensed in the system.
Sequence of Steps#
Step 1: Manage Costs#
If the Costing module is properly licensed in the system, the Costs tab will be enabled on the right-hand sidebar and you will be able to define the Step costing information.
-
Optionally, modify the Step costs from the following available options:
- Step Standard Costs
- Step Standard Fixed Cost - fixed costs of using the Step.
- Step Standard Cost Per Unit - costs per processed unit in this Step. It should not include resource (machine) costs.
- Step Standard Cost Per Hour - costs of this Step per hour.
- Resource Standard Costs (Forecast)
- Resource Standard Fixed Cost - fixed costs of using this Resource.
- Resource Standard Cost Per Unit - costs per processed unit using this Resource. In principle, exclusive with Resource Cost per Hour but can be complementary.
- Resource Standard Cost Per Hour - costs per hour of using this Resource. In principle, exclusive with Resource Cost per Unit but can be complementary.
- Labor Standard Costs (Forecast)
- Labor Standard Costs Per Hour - costs per hour of using a Resource in this Step by a member of the labor force.
- Step Standard Costs
-
Select Update to complete the operation.