Scheduling Holds and Future Holds#

Scheduling can take into consideration possible holds and future holds that have been placed on Materials.

Holds#

Materials that are currently on hold can be treated one of two ways, according to the Holds Processing Mode property, defined at the Schedule level:

  • Included: Materials with holds will be considered in Scheduling normally.
  • Excluded: Materials with holds will be excluded from Scheduling.

Future Holds#

Materials that have future holds can be treated one of two ways, according to the Future Holds Processing Mode property, defined at the Schedule level:

  • Ignore: Materials will be scheduled normally, as if the future holds did not exists.
  • Stop: Materials will be scheduled only partially:
  • If the first future hold which the Material will be subject to is of state Queued, it will scheduled up until the previous Step of that future hold.
  • If the first future hold which the Material will be subject to is of state Processed, it will scheduled up until the Step of that future hold.