Scheduling Holds and Future Holds#
Scheduling can take into consideration possible holds and future holds that have been placed on Materials.
Holds#
Materials that are currently on hold can be treated one of two ways, according to the Holds Processing Mode property, defined at the Schedule level:
- Included: Materials with holds will be considered in Scheduling normally.
- Excluded: Materials with holds will be excluded from Scheduling.
Future Holds#
Materials that have future holds can be treated one of two ways, according to the Future Holds Processing Mode property, defined at the Schedule level:
- Ignore: Materials will be scheduled normally, as if the future holds did not exists.
- Stop: Materials will be scheduled only partially:
- If the first future hold which the Material will be subject to is of state Queued, it will scheduled up until the previous Step of that future hold.
- If the first future hold which the Material will be subject to is of state Processed, it will scheduled up until the Step of that future hold.