Track-out Batch#
Batch.TrackOut
Overview#
This operation is used to Track-Out a given Batch.
Setup#
No specific setup is required other than to meet the precondition of the transaction.
Preconditions#
- The Batch exists in the system and is Active.
- The Batch System State is In-Process.
- The Batch Load State is Loaded.
- All Batch Materials must be In-Process at the Batch Step and the Batch Resource must be defined.
Info
When a Batch Material is terminated while the Batch is in process, its associated Resource Job Material is removed. You can then track out the Batch for its remaining Batch Materials.
Sequence of Steps#
- Choose a In-Process Batch, then select the Track-Out button on the top ribbon.
-
A wizard will appear with the list of the Batch Items, as shown below.
-
Optionally, enter a comment for the operation.
- Select Next.
-
A wizard displaying Resource Details will appear, as shown below. Here, you can select the Resource State from the following options: Productive, Standby, or Engineering.
-
Optionally, enter a comment for the operation.
- Select Track-Out.
Info
After you Track-Out a Batch, its System State will change to Processed, as well as all the Batch Materials.

