Complete Maintenance Activity Order#
MaintenanceActivityOrder.Complete
Overview#
This operation completes the execution of a Maintenance Activity Order (MAO) which is In Progress.
Setup#
No setup is required other than to meet the preconditions of the transaction.
Preconditions#
- The MAO is in the execution state In Progress.
- The user must either belong to the MAO Owner Role or be the MAO Owner Role (either the MAO Owner Role or Owner User must be defined).
- The Checklist Instance - if any - has been completed.
- The MAO must not be included in another MAO, that is, the Parent MAO property must be
null. - All mandatory MAO parts which are part of the BOM (if any) and are not optional must be consumed in exactly the same quantity as defined in the BOM.
Sequence of Steps#
Step 1#
-
Verify the information regarding the MAOs.
Note
It is possible to select multiple MAOs before entering the Complete Maintenance Activity Order wizard.
-
The effective completion date will be set with the current date/time, but it is possible to override it.
- If the MAO is Ad hoc and there is a Root cause source defined, the user must specify a value from the defined lookup table as the root cause.
- If a state transition is associated with the entity to which the MAO is related, it is possible to change the state of the entity by selecting a new state from the list. If the state transition has Reasons associated, you can accept the suggested Reason or select another one.
- Optionally, enter a Comment.
- Select Complete to finish the transaction.
Info
Depending on the state model configuration, enabling the Resource after the completion of this MAO may trigger a different state change than expected. The system will attempt to transition the Resource to a state where the SEMI E10 attribute is set to Standby.