Complete Maintenance Activity Order#

🔒 MaintenanceActivityOrder.Complete

Overview#

This operation completes the execution of a Maintenance Activity Order (MAO) which is In Progress.

Setup#

No setup is required other than to meet the preconditions of the transaction.

Preconditions#

  • The MAO is in the execution state In Progress.
  • The user must either belong to the MAO Owner Role or be the MAO Owner Role (either the MAO Owner Role or Owner User must be defined).
  • The Checklist Instance - if any - has been completed.
  • The MAO must not be included in another MAO, that is, the Parent MAO property must be null.
  • All mandatory MAO parts which are part of the BOM (if any) and are not optional must be consumed in exactly the same quantity as defined in the BOM.
  • If the Maintenance Type of the MAO is set to Qualification and the Type Restriction Mode is set to Require Specific, the MAO can only be completed after all associated Qualification Checks are either Completed or Obsolete.

Sequence of Steps#

Step 1#

  1. Verify the information regarding the MAOs.

    Note

    It is possible to select multiple MAOs before entering the Complete Maintenance Activity Order wizard.

  2. The effective completion date will be set with the current date/time, but it is possible to override it.

  3. If the MAO is Ad hoc and there is a Root cause source defined, you must specify a value from the defined lookup table as the root cause.
  4. If a state transition is associated with the entity to which the MAO is related, it is possible to change the state of the entity by selecting a new state from the list. If the state transition has Reasons associated, you can accept the suggested Reason or select another one.
  5. Optionally, enter a Comment.
  6. Select Complete to finish the operation.

Info

Depending on the state model configuration, enabling the Resource after the completion of this MAO may trigger a different state change than expected. The system will attempt to transition the Resource to a state where the SEMI E10 attribute is set to Standby.

If a Post Maintenance Activity was defined when Adding Maintenance Activities, the system automatically executes the configured Maintenance Activity after the current MAO is completed.

Screenshot showing a completed Maintenance Activity Order (MAO) with details including zone and resource information.

When the Maintenance Type of the MAO is set to Qualification and the Type Restriction Mode is set to Require None, you must record a Pass or Fail result for each associated Qualification Check, and optionally add Remarks.

If the Qualification Checks fail, the system automatically executes the Rework Maintenance Activity Order operation for the failed MAO Qualification Checks. This is performed by selecting the Date for the execution:

Complete MAO

Afterwards, classify the Qualification Checks and complete the operation:

Classify the Qualification Checks as Pass or Fail