Skip to content

Attach Material#

🔒 Material.Attach

Overview#

This operation is used to add an existing Material as Sub-Material of another existing Material. As a naming convention, the Material being attached is referred to as Sub-Material, and the Material gaining the Sub-Material is referred to as Parent Material. The highest parent of the Parent Material is referred to as Top-Most of Parent Material.

Setup#

No special setup is required other than to meet the preconditions of the transaction.

Preconditions#

  • Both the Parent Material and Sub-Material must exist and be Active.
  • Both the Top-Most of Parent Material and the Top-Most of Sub-Material must have the CurrentTransferMaterial property set to null.
  • For the Top-Most of both the Parent Material and Sub-Material:
    • The In Transfer Order Item must be empty.
    • The Pick List Item Count must be empty.
  • The Parent and Sub-Material Package Count must be empty.
  • The Top-Most of Parent Material and the Sub-Material cannot be On Hold Or In Transit or Dispatched or In Process or In Store.
  • The Top-Most of Parent Material must be Queued or Processed.
  • The Sub-Material to be attached must have the same state as the Top-Most of Parent Material.
  • The Sub-Material must be at the same Step and Facility of the Main Material.
  • The Sub-Material to be attached must not have a Parent.
  • The Sub-Material (example: the Material being attached) cannot be associated with a Resource.
  • Top-Most Material is not of type Consumable.
  • Both the Parent and Sub-Material must have the same Primary Units and Secondary Units.
  • If the Sub-Material to be attached has associated characteristics that are greater than 0 or null, then one of these conditions must be true:
    • The characteristics of the Top-Most of Parent Material is 0 or null.
    • The Material Characteristics set of the Top-Most of Parent Material match exactly (number, name, and value) the Material Characteristics of the Sub-Material to be attached.
  • If the property Use Container Restrictions in the Step of the Material is true, the available containers will be the ones that match the restrictions applied by the context of that Step. For more information, see Contexts View or MaterialContainerTypeContext.

    Note

    The Container Used Positions must be less than the Container Max Usable Positions.

Preconditions for Bulk#

  • In addition to the preconditions mentioned above, all Sub-Materials must:

    • Be attached to the same Parent Material.
    • Have the same Form.

Sequence of Steps#

The Attach Material wizard is called from the Details page of the selected Material. Depending on the current system status, the Attach Material button may be visible on the top ribbon or under the More actions button.

Step 1#

  1. Select the Material you need.
  2. Select Attach.
  3. In the Attach Material wizard, select the Material to which the Sub-Material will be attached.
  4. Specify whether for the Sub-Material you want to:
    • AssignMaterialToContainer - if Sub-Material has no Container.
    • TransferMaterialBetweenContainers - if Sub-Material has a Container.
    • DisassociateMaterialFromContainer - if Sub-Material has a Container.
  5. In case the Sub-Material has future holds associated to it, it is necessary to define if these future holds should be copied into the Main Material.
  6. Optionally, select whether to Bypass Material Form Validation For Siblings.
  7. Select Attach to complete the operation.
  8. The system will confirm that the Sub-Material was attached successfully to the main Material.