Insert Material into Line#
Material.InsertIntoLine
Overview#
This operation is used to insert a Material into a parent Material that is tracked-in (in process) at a Line. As a naming convention, the Material to be inserted is called Child Material and the Material where the Material will be inserted is called Parent Material.
Setup#
No special setup is required other than to meet the preconditions of the transaction.
Preconditions#
-
Both the Parent Material and Child Material:
- Are TopMost, Active and Non-Template
- Are not on Hold or Stored
- Do not have a FutureAction set
- Are not a part of a Pick List or a Transfer Order
- Must be in a Line Step
- The TargetQuantity must be null
- Have the same Facility, Step, Flow, Flow Path
- Have the same PrimaryUnits and SecondaryUnits
-
Regarding the Child Material:
- It's in state Queued
- It's Dispatchable
- If the PendingReworkReturn property is true, the Child Material can only be inserted via Special Insert Material Into Line and it must be inserted into the LineReworkStep in a Material that has the same LineReworkReturnFlowVersion. Note by design at this time, the Resource is not being enforced.
Note
Because this is a more restricted and lightweight operation, there are some checks that are not performed by design (e.g.: certifications, maintenance, product blocks, time-constraints, material dependencies).
-
Regarding the Parent Material:
- It's in state InProcess
- If the Parent Material has an Experiment, the Child Material must have the same Experiment property defined.
-
Regarding the Resource current processing the Parent Material:
- Must be TopMost and of processing type Line
- Must be Active and Non-Template
- Must have the System State Up
- The Inventory Locked must be false
- The Resource Enable SubTrackin property must be true
- If the Child Material RequiredResource is set, the Parent Material Resource must be equal to that Required Resource
-
Regarding the destination Flow Path where the Child Material will be inserted:
- In the Parent Material structure Material Line Steps, there must be a valid active Material Line Step with a reference to that Flow Path
- The relationship Parent Material Form to Child Material Form must be defined in the MaterialForm table
Sequence of Steps#
Step 1#
- Select a Child Material matching the pre-conditions outlined above. Select Insert Material Into Line from the top ribbon.
- Select a Resource matching the pre-conditions outlined above.
- Select a Parent Material currently in state InProcess at the Resource where the Child Material will be inserted.
-
Review the information and select Insert to complete the transaction.
Info