Reassign Production Order Materials#
ProductionOrder.Reassign
Overview#
This operation is used to reassign one or more Materials from a Production Order.
Setup#
No special setup is required other than to meet the preconditions of the transaction.
Preconditions#
- The Material old and new (if any) Production Orders are active and in the state *Created, Released, In Progress or Completed.
- The Material old and new (if any) Production Orders must not be restricted.
- The Material to be re-assigned must be active.
- If the new (if any) Production Order has the option Validate material products set, the Materials to be assigned must have a Product which belongs to the reverse Product tree of the Production Order Product.
Sequence of Steps#
This screen captures all the information necessary to complete the operation.
- Optionally, review the Production Order details by expanding the Production Order section.
-
The grid on the left will list all the Materials that are currently associated with the Production Order. For each Material it is possible to either:
-
Remove it from the Production Order, by selecting the option to Reassign to None.
-
Assign it to another Production Order, by selecting the option Reassign to Production Order and specifying the new Production Order.
-
Press Reassign to complete the operation.
Info
It is possible to apply a change to all Materials of the Production Order by pressing the button Apply to all Materials
Info
This wizard provides the additional options:
- Apply Production Order priority to Materials - whether to set the Material priority with the Production Order priority.
- Apply Production Order planned end date to Materials - whether to set the Material due date with the Production Order due date.
- Account to old Production Order - whether the Material should still account for the old Production Order.
- Account to new Production Order - whether the Material should account for the new Production Order.
- Apply changes recursively to Sub-Materials - whether the changes apply recursively to all Sub-Materials.
- Remove from old Production Order - whether the Material will be removed from the old Production Order.