Overview#

This operation is used to reassign one or more Materials from a Production Order.

Setup#

No special setup is required other than to meet the preconditions of the transaction.

Preconditions#

  • The Material old and new (if any) Production Orders are active and in the state *Created, Released, In Progress or Completed.
  • The Material old and new (if any) Production Orders must not be restricted.
  • The Material to be re-assigned must be active.
  • If the new (if any) Production Order has the option Validate material products set, the Materials to be assigned must have a Product which belongs to the reverse Product tree of the Production Order Product.

Sequence of Steps#

This screen captures all the information necessary to complete the operation.

  1. Optionally, review the Production Order details by expanding the Production Order section.
  2. The grid on the left will list all the Materials that are currently associated with the Production Order. For each Material it is possible to either:

  3. Remove it from the Production Order, by selecting the option to Reassign to None.

  4. Assign it to another Production Order, by selecting the option Reassign to Production Order and specifying the new Production Order.

  5. Press Reassign to complete the operation.

Info

It is possible to apply a change to all Materials of the Production Order by pressing the button Apply to all Materials

ReassignProduction Order Materials

Info

This wizard provides the additional options:

  • Apply Production Order priority to Materials - whether to set the Material priority with the Production Order priority.
  • Apply Production Order planned end date to Materials - whether to set the Material due date with the Production Order due date.
  • Account to old Production Order - whether the Material should still account for the old Production Order.
  • Account to new Production Order - whether the Material should account for the new Production Order.
  • Apply changes recursively to Sub-Materials - whether the changes apply recursively to all Sub-Materials.
  • Remove from old Production Order - whether the Material will be removed from the old Production Order.