Manage Feed Steps#
Schedule.Edit
Overview#
This operation is used to define and manage the Steps that can be included in a given Schedule, instructing the scheduling engine to include the Materials that are in those Steps in the calculations.
Setup#
No specific setup is required other than to meet the precondition of the transaction.
Preconditions#
- The Scheduling module is properly licensed in the system.
- The Steps must not belong to any Area of the Schedule.
- The Steps must belong to an Area of the selected Feed Step Facility.
- There must not be more than one combination of Schedule, Feed Step and Facility.
Sequence of Steps#
Step 1: Manage Feed Steps#
- Select an appropriate Schedule, navigate to the Feed Steps section and select Manage Production Order Steps.
-
Add as many Feed Steps as you need (select in the top right of the grid to add and to remove), providing the following information for each item:
- Facility
- Step
-
Select Manage to complete the transaction and update the Schedule.