Skip to content

Material Movement Cube#

ClickHouse Cube#

  • cube_material_movement

Dimensions#

The Material Movement Cube has the following dimensions:

Field Description Primary Key Public
Enterprise Name The name of the enterprise or company.
Site Name The name of the specific site.
Facility Name The name of the facility within the site.
Facility Display Order The display order of the facility within the site.
Area Name The name of the area within the facility.
Area Display Order The display order of the area within the facility.
Step Name The name of the specific manufacturing step where the material entered.
Step Display Order The display order of the specific manufacturing step where the material entered.
Step Type The type of the specific manufacturing step where the material entered.
Material Name The name of the material being processed.
Material Type The type of the material being processed.
Material Form The form of the material being processed.
Material Primary Units The primary units of the material being processed.
Resource Name The name of the resource (e.g., machine or equipment) involved in processing the material.
Resource ResourceType The resource user type for the resource.
Date Entered Step The ticks for the date and time when the material first entered the step.
Date Entered Step The date and time when the material first entered the step.
In Process Time The date and time when the material first entered the in process state.
Processed Time The date and time when the material first entered the processed state.
Calendar Name The name of the calendar used to process the material.
Calendar Day FY The calendar fiscal year during which the material is being processed.
Calendar Day FQ The calendar fiscal quarter during which the material is being processed.
Calendar Day FM The calendar fiscal month during which the material is being processed.
Calendar Day FW The calendar fiscal week during which the material is being processed.
Calendar Day The ticks for the calendar day during which the material is being processed.
Calendar Day The calendar day during which the material is being processed.
Shift Name The work shift during which the material is being processed.
Product Name The name of the Product of the material being processed.
Product Type The type of the Product of the material being processed.
Product Group Name The name of the Product Group of the material being processed.
Product Group Type The type of the Product Group of the material being processed.

Table: Material Movement Dimensions

Measures#

The Material Movement Cube has the following measures:

Field Description Primary Key Public Type Formula
Record Count Total number of records representing material movements. count
Queued Primary Quantity Total primary quantity of materials queued for processing. sum QueuedPrimaryQty
Queued Secondary Quantity Total secondary quantity of materials queued for processing. sum QueuedSecondaryQty
Queued Sub-Materials Primary Quantity Total primary quantity of sub-materials queued for processing. sum QueuedSubMaterialsPrimaryQty
Queued Sub-Materials Secondary Quantity Total secondary quantity of sub-materials queued for processing. sum QueuedSubMaterialsSecondaryQty
Dispatched Primary Quantity Total primary quantity of materials dispatched for the next step. sum DispatchedPrimaryQty
Dispatched Secondary Quantity Total secondary quantity of materials dispatched for the next step. sum DispatchedSecondaryQty
Dispatched Sub-Materials Primary Quantity Total primary quantity of sub-materials dispatched for the next step. sum DispatchedSubMaterialsPrimaryQty
Dispatched Sub-Materials Secondary Quantity Total secondary quantity of sub-materials dispatched for the next step. sum DispatchedSubMaterialsSecondaryQty
In Process Primary Quantity Total primary quantity of materials currently in process. sum InProcessPrimaryQty
In Process Secondary Quantity Total secondary quantity of materials currently in process. sum InProcessSecondaryQty
In Process Sub-Materials Primary Quantity Total primary quantity of sub-materials currently in process. sum InProcessSubMaterialsPrimaryQty
In Process Sub-Materials Secondary Quantity Total secondary quantity of sub-materials currently in process. sum InProcessSubMaterialsSecondaryQty
Processed Primary Quantity Total primary quantity of materials processed. sum ProcessedPrimaryQty
Processed Secondary Quantity Total secondary quantity of materials processed. sum ProcessedSecondaryQty
Processed Sub-Materials Primary Quantity Total primary quantity of sub-materials processed. sum ProcessedSubMaterialsPrimaryQty
Processed Sub-Materials Secondary Quantity Total secondary quantity of sub-materials processed. sum ProcessedSubMaterialsSecondaryQty
Queued Duration Time Total time for materials in the queue. sum QueuedLag
Dispatched Duration Time Total time for materials after being dispatched before processing. sum DispatchedLag
In Process Duration Time Total time for materials while in process. sum InProcessLag
Processed Duration Time Total time for materials after being processed. sum ProcessedLag
Cycle Time Cycle time for the materials. sum QueuedLag + DispatchedLag + InProcessLag + ProcessedLag
Average Cycle Time Average cycle time for the materials. avg QueuedLag + DispatchedLag + InProcessLag + ProcessedLag
Minimum cycle Time Minimum cycle time for the materials. min QueuedLag + DispatchedLag + InProcessLag + ProcessedLag
Maximum cycle Time Maximum cycle time for the materials. max QueuedLag + DispatchedLag + InProcessLag + ProcessedLag
Dispatch Count Total number of dispatches for materials to the next step. sum DispatchCount
Track-In Count Total number of times materials were tracked into the step. sum TrackInCount
Track-Out Count Total number of times materials were tracked out of the step. sum TrackOutCount
Abort Process Count Total number of aborts during material processing in a given Step. sum AbortProcessCount
Rework Count Total number of reworks performed on materials in a given Step. sum ReworkCount
Terminated Process Count Total number of terminated operations in a given Step. sum TerminatedCount
Step Output Primary Quantity Total primary output quantity of materials from a step. sum StepOutputPrimaryQty
Step Output Secondary Quantity The total secondary quantity of materials output from a step. This represents one of the two quantities that translate to each other for the material. sum StepOutputSecondaryQty
Step Output Sub-Materials Primary Quantity The total primary quantity of sub-materials output from a step. This represents one of the two quantities that translate to each other for the sub-material. sum StepOutputSubMaterialsPrimaryQty
Step Output Sub-Materials Secondary Quantity The total secondary quantity of sub-materials output from a step. This represents one of the two quantities that translate to each other for the sub-material. sum StepOutputSubMaterialsSecondaryQty
Primary Quantity Losses The total primary quantity of material losses. This represents the amount of material lost during the processing steps. sum Material_Primary_Quantity_Losses
Secondary Quantity Losses The total secondary quantity of material losses. This represents the amount of material lost during the processing steps. sum Material_Secondary_Quantity_Losses
Yield The percentage yield of processed materials relative to the total quantity of materials input, accounting for primary quantity losses. number CASE WHEN ({processed_primary_quantity} + {primary_quantity_losses}) != 0 THEN {processed_primary_quantity}/({processed_primary_quantity} + {primary_quantity_losses}) * 100.0 ELSE 0 END
Total Primary Quantity Losses The total primary quantity of material and sub-material losses. This represents the amount of material lost during the processing steps. sum Material_Primary_Quantity_Losses + Material_SubMaterials_Primary_Quantity_Losses
Step Output Total Primary Quantity Total primary output quantity of materials and sub-materials from a step. sum StepOutputPrimaryQty + StepOutputSubMaterialsPrimaryQty
Total Processed Primary Quantity Total processed primary quantity of materials and sub-materials. sum ProcessedPrimaryQty + ProcessedSubMaterialsPrimaryQty
Rate Of Quality The Rate of Quality for the period - one of the components of Overall Equipment Effectiveness (OEE), calculated as the percentage of processed primary quantity relative to the total of processed primary quantity and primary quantity losses. number {_rate_of_quality} * 100.0
_Rate Of Quality Internal Use - The Rate of Quality for the period - one of the components of Overall Equipment Effectiveness (OEE), calculated as the percentage of processed primary quantity relative to the total of processed primary quantity and primary quantity losses. number CASE WHEN ({total_processed_primary_quantity} + {total_primary_quantity_losses}) != 0 THEN {total_processed_primary_quantity}/({total_processed_primary_quantity} + {total_primary_quantity_losses}) ELSE 0 END
Ideal Cycle Time The ideal cycle time for processing materials. sum multiplyDecimal(Material_IdealCycleTime, (ProcessedPrimaryQty + ProcessedSubMaterialsPrimaryQty))

Table: Material Movement Measures

Public Keys

All dimensions or measures with the "Public" column marked with a icon must not be used. These are private dimensions/measures, used for intermediate calculations before the aggregations are performed. Using them will result in a query failure.