Product Planning and WIP Cube#

ClickHouse Cube#

  • cube_product_plans_wip

Dimensions#

The Product Planning and WIP Cube has the following dimensions:

Field Description Primary Key Public
Enterprise Name The name of the enterprise or company.
Site Name The name of a specific site or location.
Facility Name The name of the facility within the site.
Area Name The name of the area within the facility.
Area Display Order The Area's order within the process flow.
Product Name Product used as Plan Item defined in terms of the production item.
Product Type Product's type.
Step Name Steps used on the planning.
Step Display Order The Step's order within the process flow.
Plan Level To view information organized by Product or Product Group.
Material Type Material's type.
Plan Name Plan name.

Table: Product Planning and WIP Dimensions

Measures#

The Product Planning and WIP Cube has the following measures:

Field Description Primary Key Public Type Formula
Daily Plan Forecasted production volumes for each product. sum Daily_Plan
Daily Volume Material Quantity that moved out of the step. max Daily_Volume
Total WIP Current instant total WIP. max Total_WIP
Total Hold Current wip on hold. max Total_Hold
Total Free WIP Current wip excluding hold status. max Total_Free_WIP
Total_Rework Current wip in rework. max Total_Rework
Processed Primary Quantity Processed primary quantity of materials processed. max Processed_Primary_Quantity
Primary Quantity Losses The total primary quantity of material losses. This represents the amount of material lost during the processing steps. max Primary_Quantity_Losses
Yield The percentage yield of processed materials relative to the total quantity of materials input, accounting for primary quantity losses. number CASE WHEN ({processed_primary_quantity} + {primary_quantity_losses}) > 0 THEN {processed_primary_quantity}/({processed_primary_quantity} + {primary_quantity_losses}) * 100.0 ELSE 0 END
Week To Date Cumulative volume from the beginning or the fiscal week until the present day. sum Wtd
Week To Date Plan Planned Volume from the beginning of the fiscal week of the present day. sum wP
Time to completion Simple estimation (little's law) to determine time expected to finish current WIP by step, in minutes. max Time_To_Completion

Table: Product Planning and WIP Measures

Public Keys

All dimensions or measures with the "Public" column marked with a icon must not be used. These are private dimensions/measures, used for intermediate calculations before the aggregations are performed. Using them will result in a query failure.