Resource States with Non Working Times Cube#

ClickHouse Cube#

  • cube_resourcestates_non_working_times

Dimensions#

The Resource States with Non Working Times Cube has the following dimensions:

Field Description Primary Key Public
Operation The specific operation or process being tracked.
Enterprise Name The name of the enterprise or company.
Site Name The name of the specific site or location.
Facility Name The name of the facility within the site.
Facility DisplayOrder The Display Order of the facility
Area Name The name of the area within the facility.
Area DisplayOrder The Display Order of the area
Resource Name The name of the resource (e.g., machine or equipment) being monitored.
Resource ResourceType The resource user type for the resource.
Resource DisplayOrder The Display Order of the resource (e.g., machine or equipment) being monitored.
Model The model number or identifier of the resource.
Manufacturer The manufacturer of the resource.
Class The classification or category of the resource.
Shift Name The name of the work shift during which the resource is operating.
SEMI E10 State The SEMI E10 state of the resource, indicating its operational status.
SEMI E58 State The SEMI E58 state of the resource, indicating its current condition.
Basic State The basic state of the resource, such as 'up' or 'down'.
Start Time The start time of the resource state.
End Time The end time of the resource state.
Calendar Name The specific calendar name associated with the resource state.
Calendar Day FY The calendar fiscal year associated with the resource state.
Calendar Day FQ The calendar fiscal quarter associated with the resource state.
Calendar Day FM The calendar fiscal month associated with the resource state.
Calendar Day FW The calendar fiscal week associated with the resource state.
Calendar Day The specific calendar day associated with the resource state.

Table: Resource States with Non Working Times Dimensions

Measures#

The Resource States with Non Working Times Cube has the following measures:

Field Description Primary Key Public Type Formula
Record Count Total number of records in the dataset. count
Working Time Total working time of the resource. sum WorkingTime
SEMI E10 Engineering Working Time Total time under SEMI E10 engineering state. sum SEMIE10State_EngineeringDuration
SEMI E10 Engineering Working Time Total working time under SEMI E10 engineering state. sum SEMIE10State_EngineeringWorkingTime
SEMI E10 Non-Scheduled Working Time Total working time under SEMI E10 non-scheduled state. sum SEMIE10State_NonscheduledWorkingTime
SEMI E10 Productive Working Time Total time under SEMI E10 productive state. sum SEMIE10State_ProductiveDuration
SEMI E10 Productive Working Time Total working time under SEMI E10 productive state. sum SEMIE10State_ProductiveWorkingTime
SEMI E10 Scheduled Down Working Time Total working time during scheduled downtime under SEMI E10 state. sum SEMIE10State_ScheduledDownWorkingTime
SEMI E10 Standby Time Total time during standby under SEMI E10 state. sum SEMIE10State_StandbyDuration
SEMI E10 Standby Working Time Total working time during standby under SEMI E10 state. sum SEMIE10State_StandbyWorkingTime
SEMI E10 Unscheduled Down Working Time Total working time during unscheduled downtime under SEMI E10 state. sum SEMIE10State_UnscheduledDownWorkingTime
Basic State Down Working Time Total working time during the down state. sum BasicState_DownWorkingTime
Basic State Non-Scheduled Working Time Total working time during non-scheduled periods under the basic state. sum BasicState_NonscheduledWorkingTime
Basic State Up Working Time Total working time during the up state. sum BasicState_UpWorkingTime
Non-Working Time Total non-working time of the resource. sum NonWorkingTime
SEMI E10 Engineering Non-Working Time Total non-working time under SEMI E10 engineering state. sum SEMIE10State_EngineeringNonWorkingTime
SEMI E10 Non-Scheduled Non-Working Time Total non-working time under SEMI E10 non-scheduled state. sum SEMIE10State_NonscheduledNonWorkingTime
SEMI E10 Productive Non-Working Time Total non-working time under SEMI E10 productive state. sum SEMIE10State_ProductiveNonWorkingTime
SEMI E10 Scheduled Down Non-Working Time Total non-working time during scheduled downtime under SEMI E10 state. sum SEMIE10State_ScheduledDownNonWorkingTime
SEMI E10 Standby Non-Working Time Total non-working time during standby under SEMI E10 state. sum SEMIE10State_StandbyNonWorkingTime
SEMI E10 Unscheduled Down Non-Working Time Total non-working time during unscheduled downtime under SEMI E10 state. sum SEMIE10State_UnscheduledDownNonWorkingTime
Basic State Down Non-Working Time Total non-working time during the down state. sum BasicState_DownNonWorkingTime
Basic State Non-Scheduled Non-Working Time Total non-working time during non-scheduled periods under the basic state. sum BasicState_NonscheduledNonWorkingTime
Basic State Up Non-Working Time Total non-working time during the up state. sum BasicState_UpNonWorkingTime
Duration The Duration sum Duration
SEMI E10 Scheduled Down Duration Total Duration during scheduled downtime under SEMI E10 state. sum SEMIE10State_ScheduledDownDuration
SEMI E10 Uncheduled Down Duration Total Duration of unscheduled downtime under SEMI E10 state. sum SEMIE10State_UnscheduledDownDuration
Basic State duration Non-Working Time Total duration of non-scheduled periods under the basic state. sum BasicState_NonscheduledDuration
Potential Production Time The Potential Production Time for a Resource in the period, which excludes the Calendar Non Working Times and SEMI E10 Non Scheduled Times and Scheduled Down Times from the Total Time. number {duration} - {non_working_time} - {basic_state_nonscheduled_duration} + {basic_state_nonscheduled_non_working_time} - {semi_e10_state_scheduled_down_duration} + {semi_e10_state_scheduled_down_non_working_time}
Up Time The uptime for the Resource in the period number {semi_e10_state_standby_duration} + {semi_e10_state_productive_duration} + {semi_e10_state_engineering_duration}
Up Time in Working Time The uptime in working time for the Resource in the period number {semi_e10_state_standby_working_time} + {semi_e10_state_productive_working_time} + {semi_e10_state_engineering_working_time}
Up Time in Non-Working Time The uptime in non-working time for the Resource in the period number {semi_e10_state_standby_non_working_time} + {semi_e10_state_productive_non_working_time} + {semi_e10_state_engineering_non_working_time}
Down Time The downtime for the Resource in the period number {semi_e10_state_unscheduled_down_duration} + {semi_e10_state_scheduled_down_duration}
Down Time in Working Time The downtime in working time for the Resource in the period number {semi_e10_state_unscheduled_down_working_time} + {semi_e10_state_scheduled_down_working_time}
Down Time in Non-Working Time The downtime in non-working time for the Resource in the period number {semi_e10_state_unscheduled_down_non_working_time} + {semi_e10_state_scheduled_down_non_working_time}
Availability Up Time component Total uptime considered for Availability calculations. number {potential_production_time} - ( {semi_e10_state_unscheduled_down_duration} - {semi_e10_state_unscheduled_down_non_working_time} )
Availability (OEE) The Availability for the Resource in the period - following the definition of the Overall Equipment Effectiveness: OEE considers the Potential Production Time for the availability, which does not include Calendar Non Working Time, SEMI E10 Non Scheduled Time or Scheduled Down Time. number {_availability} * 100
_Availability (OEE) Internal Use - The Availability for the Resource in the period - following the definition of the Overall Equipment Effectiveness: OEE considers the Potential Production Time for the availability, which does not include Calendar Non Working Time, SEMI E10 Non Scheduled Time or Scheduled Down Time. number CASE WHEN {potential_production_time} != 0 THEN (({operating_time}) / ({potential_production_time})) ELSE 0 END
Operational Efficiency Up Time component Total uptime considered for Operational Efficiency calculations. number {semi_e10_state_productive_working_time} + {semi_e10_state_engineering_working_time}
Operational Efficiency (OEE) The Operational Efficiency for the Resource in the period - following the definition of the Overall Equipment Effectiveness: OEE considers the Potential Production Time for the availability, which does not include Calendar Non Working Time, SEMI E10 Non Scheduled Time or Scheduled Down Time number {_operational_efficiency} * 100
_Operational Efficiency (OEE) Internal Use - The Operational Efficiency for the Resource in the period - following the definition of the Overall Equipment Effectiveness: OEE considers the Potential Production Time for the availability, which does not include Calendar Non Working Time, SEMI E10 Non Scheduled Time or Scheduled Down Time number CASE WHEN {operating_time} != 0 THEN (({net_operating_time}) / ({operating_time})) ELSE 0 END
Rate Efficiency The Rate Efficiency for the Resource in the period - one of the subcomponents of Performance Efficiency, which in turn is one the components of OEE number {_rate_efficiency} * 100
_Rate Efficiency Internal Use - The Rate Efficiency for the Resource in the period - one of the subcomponents of Performance Efficiency, which in turn is one the components of OEE number CASE WHEN {net_operating_time} != 0 THEN {material_movement.ideal_cycle_time}/{net_operating_time} ELSE 0 END
Performance Efficiency (OEE) The Performance Efficiency for the Resource in the period - following the definition of the Overall Equipment Effectiveness: OEE considers the Potential Production Time for the availability, which does not include Calendar Non Working Time, SEMI E10 Non Scheduled Time or Scheduled Down Time number {_performance_efficiency} * 100
_Performance Efficiency (OEE) Internal Use - The Performance Efficiency for the Resource in the period - following the definition of the Overall Equipment Effectiveness: OEE considers the Potential Production Time for the availability, which does not include Calendar Non Working Time, SEMI E10 Non Scheduled Time or Scheduled Down Time number CASE WHEN {operating_time} != 0 THEN {material_movement.ideal_cycle_time}/{operating_time} ELSE 0 END
OEE Overall Equipment Effectiveness - given by Availability (OEE) x Performance x Quality. Availability (OEE) considers the Actual Production Time (Total Time minus Non Working Times, NonScheduled Times and Scheduled Down Times) as Available Time number {_availability} * {_performance_efficiency} * {material_movement._rate_of_quality} * 100

Table: Resource States with Non Working Times Measures

Public Keys